1 00:00:02,100 --> 00:00:13,390 [Music] 2 00:00:18,800 --> 00:00:16,340 Saturn one 1b quarterly film report 3 00:00:23,590 --> 00:00:18,810 number 25 covers progress during the 4 00:00:25,490 --> 00:00:23,600 period July August September 1965 5 00:00:27,230 --> 00:00:25,500 highlighting this quarter was the 6 00:00:30,919 --> 00:00:27,240 successful launch and flight of the 7 00:00:32,569 --> 00:00:30,929 tenth Saturn 1s a10 successfully closing 8 00:00:35,299 --> 00:00:32,579 out the Saturn one launch vehicle 9 00:00:38,420 --> 00:00:35,309 program with ten successes out of ten 10 00:00:40,160 --> 00:00:38,430 scheduled launches late last quarter the 11 00:00:43,250 --> 00:00:40,170 launch vehicle had been erected at the 12 00:00:45,440 --> 00:00:43,260 Cape and pre-launch testing started the 13 00:00:47,450 --> 00:00:45,450 spacecraft consisting of Pegasus see 14 00:00:50,750 --> 00:00:47,460 within the boilerplate service module 15 00:00:54,049 --> 00:00:50,760 plus the command module was erected atop 16 00:00:56,959 --> 00:00:54,059 s 810 on July 2nd the overall flight 17 00:00:58,479 --> 00:00:56,969 objectives of Si 10 were to continue 18 00:01:01,400 --> 00:00:58,489 development of the launch vehicle 19 00:01:04,520 --> 00:01:01,410 iterative guidance mode continued 20 00:01:06,620 --> 00:01:04,530 evaluation of system accuracy and place 21 00:01:09,080 --> 00:01:06,630 the Pegasus meteoroid technology 22 00:01:11,149 --> 00:01:09,090 satellite in near-earth orbit the 23 00:01:14,440 --> 00:01:11,159 function of the Pegasus is to provide 24 00:01:16,990 --> 00:01:14,450 meteoroid data in near-earth space 25 00:01:19,429 --> 00:01:17,000 pre-launch checkout of s and progressed 26 00:01:22,190 --> 00:01:19,439 satisfactorily following checkout 27 00:01:24,859 --> 00:01:22,200 countdown demonstration test excessively 28 00:01:30,830 --> 00:01:24,869 completed countdown began within the 29 00:01:33,200 --> 00:01:30,840 scheduled time frame sa 10 liftoff 30 00:01:36,499 --> 00:01:33,210 occurred July 30th at 8:00 a.m. Eastern 31 00:01:38,270 --> 00:01:36,509 Standard Time the first stage the second 32 00:01:42,200 --> 00:01:38,280 manufactured by the Chrysler Corporation 33 00:01:46,520 --> 00:01:42,210 burned for a 148 seconds separated and 34 00:01:49,639 --> 00:01:46,530 fell away the Douglas built second stage 35 00:01:52,130 --> 00:01:49,649 burned about 480 seconds obtaining 36 00:01:55,160 --> 00:01:52,140 programmed cutoff velocity and altitude 37 00:01:58,490 --> 00:01:55,170 stage performance was normal placing the 38 00:02:00,319 --> 00:01:58,500 Pegasus in the required orbit the 39 00:02:02,780 --> 00:02:00,329 following scene is from Pegasus B 40 00:02:05,389 --> 00:02:02,790 kinescope the Apollo command and service 41 00:02:08,180 --> 00:02:05,399 module jettisons mechanically and like 42 00:02:10,639 --> 00:02:08,190 its predecessors pegasus sees wings were 43 00:02:12,320 --> 00:02:10,649 deployed Pegasus C is presently 44 00:02:13,550 --> 00:02:12,330 obtaining information concerning 45 00:02:15,710 --> 00:02:13,560 quantity and 46 00:02:18,740 --> 00:02:15,720 Trading ability of meteoroids in 47 00:02:20,990 --> 00:02:18,750 near-earth space the successful launch 48 00:02:24,110 --> 00:02:21,000 of the tenth and final Saturn one launch 49 00:02:26,420 --> 00:02:24,120 vehicle sa 10 closed out one of the most 50 00:02:29,089 --> 00:02:26,430 successful R&D programs in the history 51 00:02:31,100 --> 00:02:29,099 of rocketry the Saturn one program 52 00:02:34,009 --> 00:02:31,110 conceived to develop a heavy launch 53 00:02:36,470 --> 00:02:34,019 vehicle compiled an unprecedented flight 54 00:02:39,140 --> 00:02:36,480 record of 10 successful flights out of 55 00:02:41,420 --> 00:02:39,150 10 scheduled launches the Saturn 1 56 00:02:43,670 --> 00:02:41,430 program has provided more than a heavy 57 00:02:46,009 --> 00:02:43,680 launch vehicle it has provided the 58 00:02:51,170 --> 00:02:46,019 technological base now being used in 59 00:02:53,210 --> 00:02:51,180 developing Saturn 1b and Saturn 5 the 60 00:02:56,420 --> 00:02:53,220 Saturn 1 program began at the army 61 00:02:58,280 --> 00:02:56,430 ballistic missile agency in 1958 under 62 00:03:01,309 --> 00:02:58,290 the leadership of dr. Wernher von Braun 63 00:03:03,320 --> 00:03:01,319 and Major General John B Medeiros the 64 00:03:07,520 --> 00:03:03,330 purpose of the program under Advanced 65 00:03:09,890 --> 00:03:07,530 Research Projects Agency order 1459 was 66 00:03:12,229 --> 00:03:09,900 to develop a 1 and 1/2 million pound 67 00:03:14,809 --> 00:03:12,239 thrust clustered engine first stage 68 00:03:16,550 --> 00:03:14,819 shortly thereafter the program was 69 00:03:18,590 --> 00:03:16,560 expanded to the development of a 70 00:03:23,000 --> 00:03:18,600 reliable three-stage heavy launch 71 00:03:25,160 --> 00:03:23,010 vehicle for scientific payloads during 72 00:03:26,840 --> 00:03:25,170 the next months studies were made to 73 00:03:29,630 --> 00:03:26,850 determine the most expeditious manner 74 00:03:32,120 --> 00:03:29,640 for using existing tooling hardware and 75 00:03:34,250 --> 00:03:32,130 facilities the new facilities that would 76 00:03:36,949 --> 00:03:34,260 be required for testing this new and 77 00:03:39,050 --> 00:03:36,959 large vehicle and the optimum upper 78 00:03:41,120 --> 00:03:39,060 stages one of the results of these 79 00:03:43,280 --> 00:03:41,130 studies was the awarding of a contract 80 00:03:45,610 --> 00:03:43,290 to the Douglas Aircraft Company to 81 00:03:50,000 --> 00:03:45,620 develop and manufacture the second stage 82 00:03:52,280 --> 00:03:50,010 Douglas began work immediately during 83 00:03:53,770 --> 00:03:52,290 the same time period ABMA started 84 00:03:56,420 --> 00:03:53,780 development of the first stage 85 00:03:59,449 --> 00:03:56,430 consisting of a cluster of nine tanks 86 00:04:01,729 --> 00:03:59,459 and eight h1 engines the engines were an 87 00:04:03,770 --> 00:04:01,739 improved version of the engine used for 88 00:04:06,259 --> 00:04:03,780 the Jupiter and other military missiles 89 00:04:10,629 --> 00:04:06,269 the first stage manufactured was a 90 00:04:12,800 --> 00:04:10,639 static firing test stage during march 91 00:04:15,170 --> 00:04:12,810 1960 technical and administrative 92 00:04:18,229 --> 00:04:15,180 control of the saturn program was 93 00:04:19,759 --> 00:04:18,239 transferred from ARPA to NASA in July 94 00:04:22,580 --> 00:04:19,769 the George C Marshall Space Flight 95 00:04:24,529 --> 00:04:22,590 Center it was activated the nucleus of 96 00:04:26,670 --> 00:04:24,539 the center was the von braun team of 97 00:04:30,910 --> 00:04:26,680 rocket experts 98 00:04:32,590 --> 00:04:30,920 in March 1960 test stage static firing 99 00:04:35,470 --> 00:04:32,600 was started with the firing of two 100 00:04:37,870 --> 00:04:35,480 engines in April all eight engines were 101 00:04:40,510 --> 00:04:37,880 successfully fired throughout the 102 00:04:42,700 --> 00:04:40,520 program the stage was constantly used to 103 00:04:45,310 --> 00:04:42,710 static test modifications and design 104 00:04:48,400 --> 00:04:45,320 changes to ensure a more reliable 105 00:04:53,050 --> 00:04:48,410 vehicle a final acceptance firing was 106 00:04:55,330 --> 00:04:53,060 held in late 1962 Assembly of the first 107 00:04:59,350 --> 00:04:55,340 stage sa one got underway 108 00:05:01,720 --> 00:04:59,360 may 26 1960 following final assembly and 109 00:05:03,610 --> 00:05:01,730 fight qualification testing the first 110 00:05:07,540 --> 00:05:03,620 Marshall built booster was shipped to 111 00:05:09,700 --> 00:05:07,550 Cape Canaveral August 1961 the stage was 112 00:05:12,010 --> 00:05:09,710 shipped by a barge specially built and 113 00:05:16,150 --> 00:05:12,020 modified to move the large flight stage 114 00:05:18,340 --> 00:05:16,160 a few months earlier during may 1961 the 115 00:05:20,260 --> 00:05:18,350 Saturn one was changed from a three 116 00:05:23,380 --> 00:05:20,270 stage scientific satellite launch 117 00:05:26,560 --> 00:05:23,390 vehicle to a two stage man rated vehicle 118 00:05:28,600 --> 00:05:26,570 to support the Apollo program the design 119 00:05:31,150 --> 00:05:28,610 changes caused this decision to be 120 00:05:33,760 --> 00:05:31,160 effective with the fifth flight at Cape 121 00:05:37,630 --> 00:05:33,770 Canaveral sa 1 was erected on the pad 122 00:05:41,860 --> 00:05:37,640 with water ballasted upper stages at 123 00:05:44,380 --> 00:05:41,870 10:06 a.m. October 27th 1961 the first 124 00:05:46,480 --> 00:05:44,390 Saturn one was launched the flight 125 00:05:52,240 --> 00:05:46,490 lasted eight minutes and was considered 126 00:05:57,880 --> 00:05:52,250 highly successful a second Saturn one 127 00:06:03,719 --> 00:05:57,890 was launched April 25th 1962 a third 128 00:06:09,490 --> 00:06:03,729 November 16 1962 and a fourth March 28th 129 00:06:11,050 --> 00:06:09,500 1963 all were successful flight testing 130 00:06:13,210 --> 00:06:11,060 of these vehicles allowed for the 131 00:06:15,029 --> 00:06:13,220 continual development of the first stage 132 00:06:17,969 --> 00:06:15,039 including testing of structures 133 00:06:19,960 --> 00:06:17,979 propulsion system and instrumentation 134 00:06:22,480 --> 00:06:19,970 verification of ground support equipment 135 00:06:24,909 --> 00:06:22,490 and development of an engine out 136 00:06:27,010 --> 00:06:24,919 capability a developed engine out 137 00:06:28,690 --> 00:06:27,020 capability would allow the Saturn to 138 00:06:31,120 --> 00:06:28,700 complete its mission with the loss of 139 00:06:35,140 --> 00:06:31,130 one engine by diverting the propellant 140 00:06:36,820 --> 00:06:35,150 to the remaining engines meanwhile the 141 00:06:38,950 --> 00:06:36,830 Douglas Aircraft Company continued 142 00:06:39,870 --> 00:06:38,960 developments tests and manufacture of 143 00:06:42,840 --> 00:06:39,880 the second stage 144 00:06:44,850 --> 00:06:42,850 called the s4 following testing and 145 00:06:48,210 --> 00:06:44,860 acceptance Doug they shipped the first 146 00:06:50,190 --> 00:06:48,220 s4 stage by guppy to the Cape for mating 147 00:06:54,510 --> 00:06:50,200 with the fifth Saturn one first stage 148 00:06:56,730 --> 00:06:54,520 the s4 stage was powered by six rl10 a3 149 00:06:59,280 --> 00:06:56,740 engines produced by Pratt & Whitney 150 00:07:01,710 --> 00:06:59,290 aircraft that burned liquid hydrogen and 151 00:07:04,830 --> 00:07:01,720 liquid oxygen producing a thrust of 152 00:07:07,230 --> 00:07:04,840 90,000 pounds this stage was the largest 153 00:07:11,930 --> 00:07:07,240 vehicle using high-energy propellants at 154 00:07:14,760 --> 00:07:11,940 the time sa5 was launched January 29th 155 00:07:17,700 --> 00:07:14,770 1964 it made a near-perfect flight 156 00:07:20,280 --> 00:07:17,710 placing more than 37 thousand pounds the 157 00:07:22,560 --> 00:07:20,290 most weight ever into Earth orbit other 158 00:07:25,200 --> 00:07:22,570 milestones included first instrument 159 00:07:30,120 --> 00:07:25,210 unit first redesigned first stage and 160 00:07:33,690 --> 00:07:30,130 initial use of Launch Complex 37 be 1/6 161 00:07:35,400 --> 00:07:33,700 Saturn was launched May 28 1964 again 162 00:07:38,430 --> 00:07:35,410 with the first and second stages live 163 00:07:40,920 --> 00:07:38,440 and an orbiting package exceeding 37 164 00:07:43,010 --> 00:07:40,930 thousand pounds part of this package was 165 00:07:46,320 --> 00:07:43,020 an early model of an Apollo spacecraft 166 00:07:50,580 --> 00:07:46,330 the flight terminated the Saturn one R&D 167 00:07:52,950 --> 00:07:50,590 flights or flights ahead of schedule sa 168 00:07:56,370 --> 00:07:52,960 7 the first operational flight vehicle 169 00:07:58,830 --> 00:07:56,380 was launched September 18 1964 and was 170 00:08:03,060 --> 00:07:58,840 highly successful all major test 171 00:08:06,570 --> 00:08:03,070 objectives were met sa nine launched on 172 00:08:08,870 --> 00:08:06,580 February 16 1965 placed into orbit a 173 00:08:11,040 --> 00:08:08,880 Pegasus satellite designed to obtain 174 00:08:13,470 --> 00:08:11,050 micrometeoroid information concerning 175 00:08:15,960 --> 00:08:13,480 quantity and penetrating ability in the 176 00:08:17,550 --> 00:08:15,970 near Earth orbit the satellite was 177 00:08:20,550 --> 00:08:17,560 developed by fairchild hiller 178 00:08:24,810 --> 00:08:20,560 under MSFC management for NASA's office 179 00:08:27,030 --> 00:08:24,820 of advanced technology the si8 Buster 180 00:08:29,640 --> 00:08:27,040 was assembled checked out and tested at 181 00:08:31,440 --> 00:08:29,650 Marshalls Michou facilities the Chrysler 182 00:08:34,110 --> 00:08:31,450 built Buster was the first industry 183 00:08:36,990 --> 00:08:34,120 produced first stage following a 184 00:08:39,709 --> 00:08:37,000 contractual agreement in November 1961 185 00:08:41,880 --> 00:08:39,719 Mishu was activated shortly thereafter 186 00:08:45,990 --> 00:08:41,890 exhibiting teamwork between the 187 00:08:49,620 --> 00:08:46,000 government and industry si8 was launched 188 00:08:52,140 --> 00:08:49,630 May 25th 1965 it was the night straight 189 00:08:53,650 --> 00:08:52,150 successful Saturn placing the second 190 00:08:56,500 --> 00:08:53,660 meteorite satellite in 191 00:08:58,840 --> 00:08:56,510 Earth orbit yes a tense flight closed 192 00:09:01,870 --> 00:08:58,850 the Saturn one program with a completely 193 00:09:03,640 --> 00:09:01,880 successful record the Saturn one program 194 00:09:06,460 --> 00:09:03,650 made great strides in guidance 195 00:09:08,530 --> 00:09:06,470 propulsion and aerodynamics and these 196 00:09:11,580 --> 00:09:08,540 capabilities are already being applied 197 00:09:13,900 --> 00:09:11,590 in the Saturn 1b and five program 198 00:09:16,240 --> 00:09:13,910 component installation for the first 199 00:09:21,240 --> 00:09:16,250 flight Saturn 1b instrument unit 200 00:09:24,100 --> 00:09:21,250 designated 201 was completed August 26 201 00:09:26,410 --> 00:09:24,110 the instrument units checkout station at 202 00:09:28,240 --> 00:09:26,420 IBM's Huntsville facility was activated 203 00:09:30,150 --> 00:09:28,250 in late August and check out of the 204 00:09:32,590 --> 00:09:30,160 first flight instrument unit began 205 00:09:34,690 --> 00:09:32,600 checkout continued through September 206 00:09:38,530 --> 00:09:34,700 with shipment to KSC scheduled for 207 00:09:40,900 --> 00:09:38,540 October are not eight that Douglass's 208 00:09:43,150 --> 00:09:40,910 Sacto facility the first flight s4b 209 00:09:44,740 --> 00:09:43,160 stage was successfully fired for a 210 00:09:47,680 --> 00:09:44,750 period of four hundred fifty-three 211 00:09:49,600 --> 00:09:47,690 seconds previously two long-duration 212 00:09:51,520 --> 00:09:49,610 static firings of the stage were 213 00:09:53,500 --> 00:09:51,530 attempted but each was terminated 214 00:09:56,170 --> 00:09:53,510 seconds after ignition due to ground 215 00:09:58,060 --> 00:09:56,180 support equipment problems post static 216 00:10:00,700 --> 00:09:58,070 modifications and checkout were then 217 00:10:02,860 --> 00:10:00,710 conducted through August 15 the stage 218 00:10:05,110 --> 00:10:02,870 was removed from the test stand August 219 00:10:06,280 --> 00:10:05,120 28 and prepared for shipment on 220 00:10:08,920 --> 00:10:06,290 September 3rd 221 00:10:10,990 --> 00:10:08,930 it was trucked to Courtland dock loaded 222 00:10:12,910 --> 00:10:11,000 aboard a barge for River shipment to San 223 00:10:14,740 --> 00:10:12,920 Francisco there the stage was 224 00:10:17,310 --> 00:10:14,750 transferred to a commercial ship for 225 00:10:19,540 --> 00:10:17,320 shipment through the Panama Canal to KSC 226 00:10:23,380 --> 00:10:19,550 structural modifications and free 227 00:10:25,120 --> 00:10:23,390 erection checks were performed at me 228 00:10:27,040 --> 00:10:25,130 shoe assembly facility the Chrysler 229 00:10:29,290 --> 00:10:27,050 Corporation completed post static 230 00:10:32,110 --> 00:10:29,300 checkout of the first Saturn 1b flight 231 00:10:36,250 --> 00:10:32,120 booster on July 19th and began preparing 232 00:10:38,590 --> 00:10:36,260 s1 b1 for shipment to KSC on August 233 00:10:40,270 --> 00:10:38,600 night the booster departed Michou by 234 00:10:42,520 --> 00:10:40,280 barge with the facilities checkout 235 00:10:44,620 --> 00:10:42,530 instrument unit this instrument unit 236 00:10:50,170 --> 00:10:44,630 arrived at me shoe in late June from 237 00:10:52,240 --> 00:10:50,180 MSFC arriving at KSC on August 24th the 238 00:10:54,700 --> 00:10:52,250 stages were prepared for erection on 239 00:10:56,980 --> 00:10:54,710 August 11th the flight booster was 240 00:10:59,350 --> 00:10:56,990 erected on launch complex 34 for 241 00:11:02,200 --> 00:10:59,360 facilities checkout I have days later 242 00:11:04,510 --> 00:11:02,210 the s4v facilities checkout stage which 243 00:11:07,120 --> 00:11:04,520 had been delivered to KSC on June 30th 244 00:11:09,220 --> 00:11:07,130 was erected atop the flight booster 245 00:11:11,650 --> 00:11:09,230 followed shortly by the facilities check 246 00:11:13,540 --> 00:11:11,660 out instrument unit after mating the 247 00:11:15,460 --> 00:11:13,550 spacecraft facilities verification 248 00:11:17,920 --> 00:11:15,470 vehicle with the Saturn 1b launch 249 00:11:19,960 --> 00:11:17,930 vehicle a checkout was conducted that 250 00:11:23,770 --> 00:11:19,970 verified the compatibility of the launch 251 00:11:25,450 --> 00:11:23,780 facilities and the space vehicle while 252 00:11:27,700 --> 00:11:25,460 pressure checks were being conducted on 253 00:11:29,580 --> 00:11:27,710 the booster September 10th excessive 254 00:11:31,900 --> 00:11:29,590 pressure was inadvertently applied 255 00:11:33,670 --> 00:11:31,910 collapsing the aft bulkhead of the 256 00:11:36,010 --> 00:11:33,680 instrument compartment of fuel tank 257 00:11:37,990 --> 00:11:36,020 number 1 upon completion of the 258 00:11:40,510 --> 00:11:38,000 remainder of checkout and removal of 259 00:11:43,000 --> 00:11:40,520 grounds test upper stages September 28 260 00:11:46,390 --> 00:11:43,010 the damaged tank was replaced with the 261 00:11:48,910 --> 00:11:46,400 tank from s1 b6 to minimize potential 262 00:11:51,430 --> 00:11:48,920 scheduled impact tank replacement was 263 00:11:54,940 --> 00:11:51,440 accomplished in one day without removing 264 00:11:57,430 --> 00:11:54,950 the booster from the launch complex two 265 00:11:59,650 --> 00:11:57,440 days later the flight s for B was 266 00:12:01,930 --> 00:11:59,660 removed from hangar AF and stacked atop 267 00:12:03,700 --> 00:12:01,940 the booster early next quarter the 268 00:12:05,530 --> 00:12:03,710 flight instrument unit will be erected 269 00:12:10,030 --> 00:12:05,540 completing the assembly of the first 270 00:12:12,030 --> 00:12:10,040 Saturn 1b launch vehicle at Marshall 271 00:12:13,990 --> 00:12:12,040 Saturn 1b dynamic test area 272 00:12:16,630 --> 00:12:14,000 modifications to the test stand 273 00:12:19,390 --> 00:12:16,640 changeover to upper stage configuration 274 00:12:22,140 --> 00:12:19,400 and reinstallation of upper stages was 275 00:12:25,090 --> 00:12:22,150 completed July 29th this configuration 276 00:12:27,360 --> 00:12:25,100 simulates the Saturn 1b flight after the 277 00:12:29,710 --> 00:12:27,370 booster is expended and falls away 278 00:12:31,900 --> 00:12:29,720 dynamic testing is conducted to verify 279 00:12:35,980 --> 00:12:31,910 the filter design of the launch vehicle 280 00:12:37,630 --> 00:12:35,990 guidance system upper stage dynamic 281 00:12:39,370 --> 00:12:37,640 testing continued through the quarter 282 00:12:42,310 --> 00:12:39,380 with completion of testing September 283 00:12:45,580 --> 00:12:42,320 11th analysis of test results is in 284 00:12:47,860 --> 00:12:45,590 process following successful 1b dynamic 285 00:12:50,500 --> 00:12:47,870 testing conversion of the upper stages 286 00:12:54,790 --> 00:12:50,510 to the proper configuration for saturn v 287 00:12:56,530 --> 00:12:54,800 dynamic testing was begun structural 288 00:12:58,120 --> 00:12:56,540 testing of the general dynamics built 289 00:13:01,450 --> 00:12:58,130 instrument unit segments was 290 00:13:04,090 --> 00:13:01,460 successfully completed by MSFC july 22nd 291 00:13:05,860 --> 00:13:04,100 the first three flight instrument unit 292 00:13:09,820 --> 00:13:05,870 structures will be built from general 293 00:13:11,740 --> 00:13:09,830 dynamic segments during August and IU 294 00:13:14,680 --> 00:13:11,750 structure designed to verify the 295 00:13:16,380 --> 00:13:14,690 structural integrity of the iu shells to 296 00:13:19,570 --> 00:13:16,390 be produced by North American Aviation 297 00:13:20,740 --> 00:13:19,580 was rejected by MSFC due to 298 00:13:23,260 --> 00:13:20,750 discrepancies 299 00:13:25,870 --> 00:13:23,270 at the direction of Marshall iBM has 300 00:13:28,810 --> 00:13:25,880 begun assembly of a second test article 301 00:13:31,150 --> 00:13:28,820 from other naa segments structural 302 00:13:35,800 --> 00:13:31,160 testing of this article will start next 303 00:13:38,440 --> 00:13:35,810 quarter at Marshall s 1 b2 underwent two 304 00:13:41,290 --> 00:13:38,450 successful routine static firings the 305 00:13:43,750 --> 00:13:41,300 first on July 9th the second on July 20 306 00:13:46,710 --> 00:13:43,760 the stage was then shipped to Michou 307 00:13:48,880 --> 00:13:46,720 August first arriving August 6 308 00:13:50,430 --> 00:13:48,890 modification and repair to the stage 309 00:13:53,530 --> 00:13:50,440 continued throughout the quarter 310 00:13:59,020 --> 00:13:53,540 delivery to KSC is scheduled for a mid 311 00:14:01,480 --> 00:13:59,030 December also at Chrysler Michou s1 b3 312 00:14:03,220 --> 00:14:01,490 checkout started late last quarter was 313 00:14:05,290 --> 00:14:03,230 completed August 14th 314 00:14:08,170 --> 00:14:05,300 preparations for stage shipment to 315 00:14:10,480 --> 00:14:08,180 Marshall continued to September 9th it 316 00:14:13,090 --> 00:14:10,490 was shipped by barge the same day just 317 00:14:16,510 --> 00:14:13,100 in advance of Hurricane Betsy arriving 318 00:14:20,950 --> 00:14:16,520 at MSFC September 16th static testing is 319 00:14:23,200 --> 00:14:20,960 scheduled for October s 1b for assembly 320 00:14:24,970 --> 00:14:23,210 continued through the quarter pre static 321 00:14:28,870 --> 00:14:24,980 check out of the stage will begin in 322 00:14:32,230 --> 00:14:28,880 early October stage fabrication for s1 323 00:14:34,480 --> 00:14:32,240 b5 was completed July 15th tank 324 00:14:37,030 --> 00:14:34,490 clustering started the same day and was 325 00:14:38,980 --> 00:14:37,040 completed in late August stage assembly 326 00:14:43,600 --> 00:14:38,990 continued through the remainder of the 327 00:14:45,520 --> 00:14:43,610 quarter s1 B 6 stage fabrication started 328 00:14:47,740 --> 00:14:45,530 last quarter continued through this 329 00:14:51,370 --> 00:14:47,750 period with tank clustering expected to 330 00:14:54,250 --> 00:14:51,380 begin next quarter s1 b7 fabrication was 331 00:14:57,190 --> 00:14:54,260 begun August 19th with fabrication of 332 00:15:00,310 --> 00:14:57,200 the lower thrust ring fabrication of the 333 00:15:02,260 --> 00:15:00,320 upper thrust ring began August 26th work 334 00:15:05,590 --> 00:15:02,270 continued through the remainder of the 335 00:15:09,250 --> 00:15:05,600 quarter at Douglass's Huntington Beach 336 00:15:12,340 --> 00:15:09,260 facility s4 b202 checkout was terminated 337 00:15:15,160 --> 00:15:12,350 August 12th following modification the 338 00:15:17,530 --> 00:15:15,170 stage was transported to sacto it was 339 00:15:19,720 --> 00:15:17,540 then offloaded and installed in beta 340 00:15:22,690 --> 00:15:19,730 test stands number three the morning of 341 00:15:24,880 --> 00:15:22,700 September 2nd pre firing operations are 342 00:15:27,010 --> 00:15:24,890 in process with static firing and 343 00:15:30,760 --> 00:15:27,020 delivery to Cape Kennedy scheduled for 344 00:15:32,890 --> 00:15:30,770 next quarter s4 b203 checkout began 345 00:15:35,970 --> 00:15:32,900 August 14th and it underwent final 346 00:15:38,830 --> 00:15:35,980 component installation through 347 00:15:40,480 --> 00:15:38,840 17204 assembly started last quarter 348 00:15:43,650 --> 00:15:40,490 continued with joining of the forward 349 00:15:46,690 --> 00:15:43,660 and aft skirt and thrust structure 350 00:15:48,700 --> 00:15:46,700 insulation of the 205 LH to tank was 351 00:15:53,110 --> 00:15:48,710 interrupted in early September to allow 352 00:15:56,140 --> 00:15:53,120 modifications and repair meanwhile s4b 353 00:15:58,240 --> 00:15:56,150 206 work progress continued with joining 354 00:16:01,270 --> 00:15:58,250 of the forward and aft common dome to 355 00:16:04,180 --> 00:16:01,280 form the common bulkhead following 356 00:16:06,880 --> 00:16:04,190 completion of saturn v s4b battleship 357 00:16:09,580 --> 00:16:06,890 testing August 20th preparations began 358 00:16:14,290 --> 00:16:09,590 for converting beta stand one prostatic 359 00:16:17,110 --> 00:16:14,300 firing s4b flight stages at IBM 360 00:16:19,270 --> 00:16:17,120 Huntsville SIU 202 component 361 00:16:21,190 --> 00:16:19,280 installation started last quarter 362 00:16:23,170 --> 00:16:21,200 continued through September with 363 00:16:25,330 --> 00:16:23,180 completion and check-out scheduled for 364 00:16:30,280 --> 00:16:25,340 next quarter shipment to the Cape is 365 00:16:31,870 --> 00:16:30,290 scheduled in December SIU 203 structural 366 00:16:34,360 --> 00:16:31,880 assembly was completed in early 367 00:16:36,490 --> 00:16:34,370 September component installation is in 368 00:16:38,110 --> 00:16:36,500 process with completion of assembly 369 00:16:41,680 --> 00:16:38,120 scheduled for next quarter 370 00:16:44,290 --> 00:16:41,690 SIU 204 structural segments furnished by 371 00:16:47,020 --> 00:16:44,300 North American Aviation were received at 372 00:16:51,490 --> 00:16:47,030 IBM September 15th and are now in 373 00:16:53,230 --> 00:16:51,500 rounding out operation at KSC mechanical 374 00:16:55,540 --> 00:16:53,240 and electrical ground support equipment 375 00:16:58,390 --> 00:16:55,550 was delivered during this quarter for 376 00:17:00,310 --> 00:16:58,400 use at launch complex 34 final 377 00:17:04,870 --> 00:17:00,320 electrical equipment installation is 378 00:17:06,970 --> 00:17:04,880 underway at marshall ii j2 engine 379 00:17:09,220 --> 00:17:06,980 delivered by Rocketdyne under wet 380 00:17:11,439 --> 00:17:09,230 initial static firing during august in 381 00:17:17,710 --> 00:17:11,449 the center's s4f eve battleship test 382 00:17:20,350 --> 00:17:17,720 stem rocket dean's j2 engine flight 383 00:17:23,370 --> 00:17:20,360 rating test series begun last quarter 384 00:17:26,350 --> 00:17:23,380 was completed July 21st at Santa Susana 385 00:17:29,260 --> 00:17:26,360 25 firings were conducted for a total 386 00:17:31,210 --> 00:17:29,270 performance of 46 minuts deficiencies 387 00:17:34,410 --> 00:17:31,220 will be corrected prior to completion of 388 00:17:37,270 --> 00:17:34,420 engine qualification frt engine number 389 00:17:40,780 --> 00:17:37,280 2023 was disassembled for engineering 390 00:17:43,510 --> 00:17:40,790 inspection in august engine number 2032 391 00:17:46,420 --> 00:17:43,520 was acceptance tested and 200k 392 00:17:47,240 --> 00:17:46,430 qualification test series began at delta 393 00:17:50,150 --> 00:17:47,250 ii test 394 00:17:54,880 --> 00:17:50,160 stand in August qualification tests are 395 00:18:00,980 --> 00:17:58,310 new device called a four axis numerical 396 00:18:03,350 --> 00:18:00,990 control measuring inspection machine is 397 00:18:06,410 --> 00:18:03,360 being used by Rocketdyne in connection 398 00:18:08,420 --> 00:18:06,420 with j2 injector assembly it permits 399 00:18:10,580 --> 00:18:08,430 time reduction as well as increased 400 00:18:13,430 --> 00:18:10,590 reliability of measuring data and 401 00:18:16,400 --> 00:18:13,440 fulfills raka dines integrated systems 402 00:18:20,140 --> 00:18:16,410 approach of using numerical control from 403 00:18:22,700 --> 00:18:20,150 design intent to finished component at 404 00:18:24,920 --> 00:18:22,710 Michou cleanup and repair of the 405 00:18:27,350 --> 00:18:24,930 facility is still under way as a result 406 00:18:29,630 --> 00:18:27,360 of Hurricane Betsy the wind and high 407 00:18:32,330 --> 00:18:29,640 water damaged facilities at miss you in 408 00:18:34,460 --> 00:18:32,340 varying degrees barges were beached 409 00:18:37,280 --> 00:18:34,470 windows were shattered and much of the 410 00:18:40,190 --> 00:18:37,290 roof damaged however no impact on 411 00:18:43,730 --> 00:18:40,200 Chrysler's s1b schedule is expected as a 412 00:18:45,380 --> 00:18:43,740 result of the hurricane Marshall Space 413 00:18:47,120 --> 00:18:45,390 Flight Center has been following with 414 00:18:49,520 --> 00:18:47,130 great interests the progress of the 415 00:18:52,310 --> 00:18:49,530 super guppy built and financed by aero 416 00:18:54,920 --> 00:18:52,320 spacelines incorporated on September 417 00:18:57,500 --> 00:18:54,930 17th the super guppy based on the Boeing 418 00:19:00,110 --> 00:18:57,510 Strato Cruiser aircraft landed at 419 00:19:02,840 --> 00:19:00,120 Redstone airstrip at Huntsville it is 420 00:19:05,930 --> 00:19:02,850 the only aircraft capable of carrying an 421 00:19:10,160 --> 00:19:05,940 S for B an assembled instrument unit and 422 00:19:12,620 --> 00:19:10,170 certain Apollo spacecraft items in 423 00:19:14,810 --> 00:19:12,630 summary the MutS July August and 424 00:19:16,940 --> 00:19:14,820 September witnessed the close of the 425 00:19:19,370 --> 00:19:16,950 highly successful Saturn one program 426 00:19:22,610 --> 00:19:19,380 entertainment of major milestones within 427 00:19:26,210 --> 00:19:22,620 the one B program preparations for the 428 00:19:29,600 --> 00:19:26,220 flight of Saturn 1b continued Saturn 1b 429 00:19:32,540 --> 00:19:29,610 stage build-up activation of Marshalls 430 00:19:34,970 --> 00:19:32,550 battleship stage for Silla assembly 431 00:19:37,280 --> 00:19:34,980 delivery and testing of ground support 432 00:19:38,840 --> 00:19:37,290 equipment and new methods of 433 00:19:44,019 --> 00:19:38,850 transportation